Name of Project Underwater Works dock Namdalseid
Year 2013
Construction Periode Apr. 2013 - Sep. 2013
Contract Amount 9,7 mill.
Oppdragsgiver Austad Maskinstasjon AS
Project Forsvarsbygg
Project Leader Eskil Austad

The work consisted of expansion and deepening for a new quay. The work consisted of loose mass dredging, drilling and blasting mountain masses, loading blasted mountains mass for filling in the foot of seabed and sealing of filling space. A total of 101,000 m3 of mass was moved in connection with the work.